Cody Schaefer 3c9343dfc8 D13 / wave 10 - the decision and the task file, before any code
Authentication moves to the domain over LDAPS. Nothing in the spec covered
auth against a directory, so per CLAUDE.md this is new scope with a new `D`
id rather than a widened old one. D1-D12 were taken.

Records what was verified against the live environment on Aug 21 rather than
assumed: LDAPS on 636 with TLS 1.3, the DC cert chain up through PRIME
CONTROLS ISSUING CA 1 to a root valid until 2051, six DCs in the SRV record,
and `prime.local` in every DC cert's SAN - which is why the client connects
to the domain name and not to a DC or an IP.

Also records why the certificate already serving the site is not usable for
this: it is a Let's Encrypt DV cert held by an OpenResty host outside this
repo, and it carries no relationship to prime.local. The question was asked
directly and the answer is not obvious, so it belongs in the record.

Eight tasks, T10.1 through T10.8. Two questions are left open in the decision
doc to be answered rather than guessed - break-glass access when the DC is
unreachable, and whether existing usernames match sAMAccountName.

Co-Authored-By: Claude Opus 5 (1M context) <noreply@anthropic.com>
2026-08-21 13:54:01 -05:00

12 KiB
Raw Permalink Blame History

Work Package Suite — Implementation Plan

Derived from Consolidated Change Request R2, August 14, 2026. Companion document for humans: WorkPackageSuite_Consolidated_Change_Request_R2.docx.

55 items, 9 waves, dependency-ordered. Read CLAUDE.md first.

Ten further items (D1-D10) were decided on August 18 2026 and are recorded in docs/waves/decisions-2026-08-18.md. 65 items total.


1. Where this came from

Three inputs were merged to produce this plan:

Source Produced IDs
13 in-app feedback comments, Aug 14 2026 (01:1101:32 PM) Functional change requests CR-001CR-018
Micron EUV review meeting, Aug 14 2026 Functional change requests and context included above
UX review of html/, Aug 14 2026, branch users/directory-super-user Rendering defects, structural findings, proposal assessment F1F6, S1S13, A1A7, B1B7, C1C4

F1F6 were verified in a browser and are reproducible. S1S13 were read from source and carry file and line references. A/B/C items assess a separately proposed UX change list; their IDs are carried over unchanged so the two documents line up.

2. Decisions (all closed)

Approved by Nick Siegfried, August 14 2026. Nothing in this plan is blocked pending a decision. Do not reopen these without a spec revision.

ID Decision
CR-009 Keep and extend Kitting. Build CR-010, CR-011, CR-012. Ship it toggled off for the Micron EUV SOP via the CR-006 section toggles. Kitting is not happening at Micron today; the team expects to get there.
CR-013 Build the lightweight material request. Line items (description, quantity, unit), needed-by date, requestor, delivery location, status. Defer the parts catalog, live inventory, and warehouse integration. Sequence after the creator has real section structure (see X6).
B7 Dissolve the creator iframe. Scheduled as T7.1, the first task of wave 7. This is the largest engineering item in the plan and most of wave 7 depends on it.
C1 Accessibility is in scope. Fold it into components already being rebuilt rather than treating it as a separate pass. Rules are in CLAUDE.md.

B7 was confirmed as "dissolve the iframe" on August 14 2026 and again at the wave 7 handoff. It is not a scheduling decision.

A second set of decisions closed on August 18 2026, at the wave 6 exit, in answer to twenty-one questions and eleven follow-ups. They are recorded in docs/waves/decisions-2026-08-18.md as D1-D10. They add three tasks and amend acceptance criteria on seven others; they do not reopen anything above.

ID Decision Amends
D1 Sample data returns to the creator, visible on the unframed page B7, S7
D2 The QA distribution list is configured in the SOP, not per work package CR-014
D3 The creator stays one page: side navigation plus collapsible sections F6
D4 Urgent surfaces the audited override; it does not bypass the constraint gate CR-003, A1
D5 Usage data moves to the admin console B7
D6 The material list uploads at SOP configuration CR-013
D7 Archived projects are readable, by project admins only B3, C1
D8 5MB a file, 2GB a project, PDFs and images, stored in the same database CR-007
D9 Ready for QA appears in Field View CR-014
D10 Email is switched on and off from the admin console CR-011, CR-014

3. Cross-track dependencies

These are the reason the wave order is what it is. Each row is a change request that cannot be built as written, or cannot be built once, until something else lands.

ID Item Depends on Type Why
X1 CR-011, CR-014 S3 Blocking Both promise an email containing a direct link to the work package. There is no pushState anywhere in the app, so no work package has an addressable URL. The emails cannot be built until URL state exists.
X2 CR-015 A1 Blocking The hold-not-clearing bug and the transition model are the same code. confirmEarlyRelease() in wp-creation-app.js is a deliberate logged-override path, so hold state is not purely derived from open constraints. Fixing them separately means fixing it twice. Corrected Aug 18 2026: this row and CLAUDE.md both cited wp-creation-app.js:1962-1972, which is deletePackage()/clearSaved(). The override path is confirmEarlyRelease(), called from the issue and release paths. Named by function so it survives the T7.1 rewrite.
X3 CR-014 A1 Sequencing Ready for QA is a new state and must land inside the guarded transition model, not beside it.
X4 CR-006 B7 Sequencing Section toggles must suppress sections inside the creator, which is an iframe child until T7.1.
X5 CR-004, CR-018 B4 Blocking Rollup by building, floor and sector cannot come from localStorage. Same data dependency that blocks the pipeline strip.
X6 CR-013 F6, A4 Sequencing A material request card is a 12th card on a form already ~4,700px tall. Build it after the form has section structure.
X7 CR-003 C3 Sequencing Priority color coding needs one source of truth for color, or Normal/High/Urgent get four implementations.
X8 CR-007 F2, S2 Blocking Offline drawing access is a tablet feature and the app bar breaks at 390px. Uploading into a form with no autosave risks losing the upload.
X9 CR-005 A4, F5, S9 Sequencing A new wizard step should be built during the stepper rebuild, with the read-only-looking fields and keyboard access fixed at the same time.
X10 CR-002, CR-016 CR-006, C3 Sequencing Both removals are expressed as toggles, not deletions. Without token consolidation the toggled styling drifts.

4. Wave order

Wave Focus File Items
0 Orientation and file map docs/waves/wave-0.md
1 Rendering defects and tooling docs/waves/wave-1.md F1 F3 F4 F5(interim) S13
2 Drawer everywhere, flat strip deleted docs/waves/wave-2.md B1 S4 F2
3 Token consolidation and button system docs/waves/wave-3.md C3 S5 A3 A5
4 Platform prerequisites docs/waves/wave-4.md B4 S3 S2 B5 S10 S11 S12
5 Launcher and SOP wizard docs/waves/wave-5.md A4 B3 S9 CR-005 CR-006 CR-002 CR-016 S1(wizard)
6 Work package general information docs/waves/wave-6.md CR-001 CR-003 CR-004 CR-018 A7
7 The creator docs/waves/wave-7.md B7 A1 CR-015 A2 A6 CR-014 CR-007 B6 S1(creator) F6 D1 D2 D3 D4 D5 D8 D9 D10
8 Kitting and material docs/waves/wave-8.md CR-009 CR-010 CR-011 CR-012 CR-013 D6 D10
9 Verification and cleanup docs/waves/wave-9.md CR-008 CR-017 S6 S7 C1 C2 C4 D7
10 Domain authentication over LDAPS docs/waves/wave-10.md D13

Wave 10 was added on August 21, 2026 and is not part of the original nine-wave sequence. It is new scope (docs/waves/decisions-2026-08-21.md), not a reinterpretation of anything above, and it depends only on wave 9 being merged rather than on any particular item in it.

Waves 1 through 4 produce almost no field-visible change. That is deliberate and it is roughly the first third of the effort. It is called out here because the Micron team is already skeptical about time spent, and silence during these waves reads as nothing happening. The trade is that waves 5 through 8 land once instead of being rebuilt, which is the failure mode the review documented at work-package-suite-styles.css:336.

Deltas from the R2 sequence

The R2 document's nine-wave table did not place A5, A7, or F6. This plan places A5 in wave 3 (it depends on token consolidation), A7 in wave 6 (it is general-information surface work), and F6 in wave 7 (its actual fix is section tabs, not a CSS change). F2 moves fully to wave 2 because B1 resolves it; wave 1 only stops the clipping.

5. Task format

Every task in a wave file follows this shape. Do not start a task that is missing a done-when list; flag it instead.

### T5.4 — CR-005: Upload location lists at SOP setup

- **Items:** CR-005
- **Depends on:** T5.1
- **Blocks:** T6.3
- **Surface:** html/ + server/
- **Files:** <paths from docs/reference/file-map.md>
- **Do:** ...
- **Do not:** ...
- **Done when:**
  - [ ] verifiable check
  - [ ] verifiable check

Done when entries must be checkable by running or looking at something. "Confirm with Nick" is never a done-when; it goes in the PR description.

6. Traceability

Every one of the 55 items appears in exactly one wave, except where noted.

Item Wave Item Wave Item Wave
CR-001 6 F1 1 A1 7
CR-002 5 F2 1 interim, 2 full A2 7
CR-003 6 F3 1 A3 1 interim, 3 full
CR-004 6 F4 1 A4 5
CR-005 5 F5 1 interim, 3 full A5 3
CR-006 5 F6 7 A6 7
CR-007 7 S1 5 wizard, 7 creator A7 6
CR-008 9 S2 4 B1 2
CR-009 8 S3 4 B2 2
CR-010 8 S4 2 B3 5
CR-011 8 S5 3 B4 4
CR-012 8 S6 9 B5 4
CR-013 8 S7 9 B6 7
CR-014 7 S8 9 B7 7
CR-015 7 S9 5 C1 all, audited in 9
CR-016 5 S10 4 C2 all, audited in 9
CR-017 9 (guard only) S11 4 C3 3
CR-018 6 S12 4 C4 4 and 9
S13 1

The August 18 items

Item Wave Task Item Wave Task
D1 7 T7.1 D6 8 T8.6
D2 7 T7.6 D7 9 T9.8
D3 7 T7.2 D8 7 T7.7
D4 7 T7.3 D9 7 T7.6
D5 7 T7.10 D10 7 and 8 T7.6, T8.3

That is 65 items across 9 waves. D10 is the only one split across two waves: the gate and its console control are built once at T7.6 and reused by T8.3.

F5 and A3 are the same defect from two sources. C1 and C2 are standing requirements enforced per task under CLAUDE.md, with a dedicated audit in wave 9. CR-017 is a do-not-remove guard rather than a build.

7. Out of scope

Deferred by decision. Do not build these, and do not treat them as gaps:

  • Full material request and inventory system, including the parts catalog and warehouse integration. Revisit once Paul Coonrod is engaged.
  • Asset database integration. Clinton's team owns that database; the Assets section is toggled off in the interim (CR-016).
  • CxAlloy or GC QA system integration. The QA gate is notification-only until CxAlloy lands.
  • P6 activity list import and validated lookup. CR-001 uses free text.

8. Inputs the plan is waiting on

These do not block code, but they block the data that makes several features real. Track them; do not invent placeholder values in their absence.

Input Owner Blocks
B100 floor and area list David Leal CR-004, CR-005 real data
Material spreadsheet Nate, via David Leal CR-013 field set
Master material workbook, preferred request format Paul Coonrod CR-013 scope
QA process of record (Excel questionnaire moving into CxAlloy) David Ramstorf, Lupe, Cody Schaefer CR-014 beyond notification

Where a list is required and not yet supplied, build the upload path (CR-005) and seed with an obviously-fake sample. Do not hardcode guessed floor names.

Status, August 18 2026. None of the four has arrived. Confirmed at the wave 6 exit that this does not change the plan: D6 extends the CR-005 upload pattern to the material list so CR-013 is buildable without Nate's spreadsheet, and the B100 list is still expected through the same door. Because no real list has ever been loaded, every location on record is sample data - which is why the free-text migration question was closed without work (decisions-2026-08-18.md, "Closed without work"). That answer does not survive the first real project.